Site overview

Szyb SW-3 is an exhaust ventilation shaft of the ZG Polkowice-Sieroszowice mine operated by KGHM Polska Miedź S.A. in Lower Silesia, Poland. Located in the Sieroszowice mining area, the shaft serves the Kopalnia Sieroszowice sector, which opened in 1980 and was merged with the Kopalnia Polkowice in 1996 to form the unified ZG Polkowice-Sieroszowice. SW-3 is listed as one of the three exhaust ventilation shafts assigned to the Polkowice-Sieroszowice section of the KGHM mine ventilation network, alongside szyby P-VII and SG-2.

Its shaft lining is of segmental tubing construction. During operational inspection of exhaust shaft linings across the KGHM system, corrosion of the tubing segment bolt heads was identified in SW-3 and recorded in engineering studies. The shaft forms part of the ten-shaft network currently operating within ZG Polkowice-Sieroszowice.

The shaft stands in open rural-industrial surroundings in the Sieroszowice sector, where its surface expression is compact and strongly functional.

Map

Map markers and directions links are provided for location reference only and do not indicate public access or permission to enter a site.
No site photograph is currently available. Images will be added as field visits are carried out.

History

Szyb SW-3 is an exhaust ventilation shaft constructed as part of the Kopalnia Sieroszowice infrastructure in the Lubin-Głogów Copper District of Lower Silesia. The Kopalnia Sieroszowice was built following a development decision in 1972 and opened for exploitation on 1 January 1980. The mine works a polymetallic copper-silver deposit in Zechstein copper-bearing shales, and in the Sieroszowice mining area the deposit contains approximately 65 g of silver per tonne of ore alongside copper.

Rock salt is also present above the ore horizon, and over 300,000 tonnes of salt are extracted annually at the mine. The Sieroszowice mine developed a network of shafts to serve both production and ventilation requirements. SW-3 functions as an exhaust ventilation shaft, drawing used air out of the underground workings.

It is one of three exhaust shafts assigned to the Polkowice-Sieroszowice section of the KGHM ventilation system, the others being szyby P-VII and SG-2. On 1 January 1996, the Kopalnia Sieroszowice was merged with the Kopalnia Polkowice to form the Zakłady Górnicze Polkowice-Sieroszowice, and SW-3 continued in service under the unified operation. The shaft has a segmental tubing lining.

Engineering studies conducted across KGHM's exhaust ventilation shaft network identified corrosion of the bolt heads connecting the tubing segments in SW-3. This condition was recorded alongside similar observations in szyby L-V, P-VII, R-VIII, R-XI and the SW-3 shaft at the combined Polkowice-Sieroszowice mine, and the findings were reported in the proceedings of the 2018 School of Underground Mining (SEP) conference. SW-3 remains an active exhaust ventilation shaft within the ZG Polkowice-Sieroszowice ten-shaft network.

Timeline

1972
Legislation

Decision to construct Kopalnia Sieroszowice

Construction of the Kopalnia Sieroszowice was decided in 1972. SW-3 was built as part of the shaft network serving the Sieroszowice mining area.
1980
Operation

Kopalnia Sieroszowice opened for exploitation

The Kopalnia Sieroszowice was formally opened for exploitation on 1 January 1980. SW-3 served as an exhaust ventilation shaft supporting the underground workings.
1990
Operation

Corrosion of tubing-segment bolt heads identified in shaft lining

Corrosion of the bolt heads connecting the tubing segments in the SW-3 shaft lining was identified and recorded. The condition was documented alongside similar findings in other KGHM exhaust ventilation shafts and reported at the 2018 School of Underground Mining conference.
1996
Operation

Merger forming ZG Polkowice-Sieroszowice; SW-3 continues as exhaust ventilation shaft

Following the merger of Kopalnia Polkowice and Kopalnia Sieroszowice on 1 January 1996, SW-3 was designated as one of three exhaust ventilation shafts serving the Polkowice-Sieroszowice section of the KGHM network, alongside szyby P-VII and SG-2.

Sources and records

SEP 2018 mining conference proceedings — exhaust shaft lining corrosion study identifying SW-3 among affected shafts at ZG Polkowice-Sieroszowice
Polish-language Wikipedia article: Zakłady Górnicze Polkowice-Sieroszowice
KGHM Polska Miedź S.A. corporate website — Polkowice-Sieroszowice mine description
Polska-org.pl historical summary of ZG Polkowice-Sieroszowice
Wikimapia locality entry: ZG Polkowice-Sieroszowice — Szyb SW-3
This researched site record is part of the HAABase Mines database. Normal personal research and browsing is welcome. Automated bulk extraction, republication, or harvesting of site text and images is not permitted without written consent.