Site overview

Schacht Fröschnitz 2 is one of two construction access shafts making up the Zwischenangriff Fröschnitzgraben, the central intermediate attack point of the 27.3-kilometre Semmering-Basistunnel railway tunnel being built by ÖBB-Infrastruktur AG between Gloggnitz in Lower Austria and Mürzzuschlag in Styria. The shaft is located in the Fröschnitzgraben valley south of Steinhaus am Semmering. Preliminary site preparation works were carried out between 2012 and 2014.

Sinking of the two shafts — Schacht Fröschnitz 1 and Schacht Fröschnitz 2 — began formally on 23 July 2015. Both shafts were sunk by blasting to a depth of approximately 400 metres and have a diameter of approximately 10 to 11 metres. At their foot a large underground cavern was excavated to serve as the assembly and launch chamber for two tunnel boring machines and as the future site of an underground emergency stop station.

Tunnel boring machine driving in the direction of Gloggnitz began in July 2018; conventional driving towards Mürzzuschlag was also carried out from this point. The shafts served throughout construction for materials supply, spoil removal, personnel access, and ventilation. Final breakthrough of the Semmering-Basistunnel was achieved on 29 November 2024.

The tunnel is scheduled for opening at the December 2029 timetable change.

The shaft stands in a narrow mountain valley, where construction platforms, access roads, and engineered slopes create a stark and functional landscape setting.

Map

Map markers and directions links are provided for location reference only and do not indicate public access or permission to enter a site.
No site photograph is currently available. Images will be added as field visits are carried out.

History

Schacht Fröschnitz 2 is one of the pair of construction access shafts constituting the Zwischenangriff Fröschnitzgraben — the intermediate attack point forming the central section of the Semmering-Basistunnel. The Semmering-Basistunnel is a 27.3-kilometre twin-tube railway tunnel connecting Gloggnitz in Lower Austria with Mürzzuschlag in Styria, crossing beneath the northern Alpine chain near the Semmering Pass. It forms part of the Baltic-Adriatic Corridor, a trans-European rail route from Gdańsk to Ravenna, and is intended to relieve the historic Semmeringbahn mountain railway while dramatically reducing journey times between Vienna and Graz.

The Fröschnitzgraben section (Baulos SBT2.1) is the longest and central of the three construction lots, with approximately 13 kilometres of tunnel driven in two directions from the Zwischenangriff. The shaft site is located south of Steinhaus am Semmering in the Fröschnitzgraben valley, within the municipality of Spital am Semmering. ÖBB-Infrastruktur AG awarded the contract for Baulos SBT2.1 in January 2014 to a joint venture (ARGE) of Implenia (Switzerland) and Swietelsky Tunnelbau GmbH, with Implenia holding a 50 per cent share and serving as technical lead; the contract value was approximately 623 million euros. Preliminary site preparation works ran from spring 2012 to 2014, including new drinking water infrastructure for the municipality of Spital am Semmering, road construction and improvement, a temporary motorway access point at the Semmering Schnellstraße, a bypass road at Steinhaus am Semmering, and preparation of the Longsgraben waste disposal site for spoil from the tunnel drives.

Sinking of Schacht Fröschnitz 1 and Schacht Fröschnitz 2 began with a ceremonial start on 23 July 2015, attended by the Federal Minister for Transport, the Styrian State Governor, and the CEO of ÖBB-Holding AG. Both shafts were sunk by blasting to a depth of approximately 400 metres — equivalent, as noted at the ceremony, to a skyscraper of over 130 floors — with a diameter of approximately 10 to 11 metres. At the foot of the shafts, a large underground cavern was excavated to serve as the operational base from which tunnel drives were launched in both directions. This cavern was subsequently fitted out as the site for an underground emergency stop station for future rail traffic through the tunnel.

The two tunnel boring machines deployed for the drive towards Gloggnitz — named "Carl" and "Ghega" — were lowered in parts through the shafts, assembled underground, and launched in July 2018. Each machine is approximately 120 metres long, weighs around 2,500 tonnes, and has a boring diameter of about ten metres. By late 2021, both machines had completed the approximately 8,100 to 8,300 metre drive eastward through the mountain. The conventional (drill-and-blast) drive towards Mürzzuschlag was carried out in parallel. Excavated material throughout the construction period was transported up through the shafts and deposited at the Longsgraben spoil depot nearby; a total of approximately 4.25 million cubic metres of material was placed there over the construction period.

The first breakthrough between the Fröschnitzgraben and Göstritz sections was achieved in June 2022. The final tunnel breakthrough of the entire Semmering-Basistunnel was completed on 29 November 2024. Fitout of the shafts that are no longer needed for operational use is being concreted over during the finishing phase. The tunnel, including the underground emergency stop station at the Fröschnitzgraben cavern, is scheduled to open with the December 2029 timetable change. Up to 12,000 people were involved in the overall construction; approximately 30,000 blasts were carried out across the project.

Timeline

2012–2014
Construction

Preliminary site preparation works

Preparatory works for the Fröschnitzgraben construction site were carried out between spring 2012 and 2014, including new drinking water infrastructure for Spital am Semmering, road construction, a temporary motorway access at the Semmering Schnellstraße, a bypass road at Steinhaus am Semmering, and preparation of the Longsgraben spoil depot.
2014
Legislation

Construction contract for Baulos SBT2.1 awarded

ÖBB-Infrastruktur AG awarded the contract for Baulos SBT2.1 (Tunnel Fröschnitzgraben) to the ARGE of Implenia and Swietelsky Tunnelbau GmbH in January 2014, with a contract value of approximately 623 million euros.
2015
Construction

Ceremonial start of shaft sinking

Shaft sinking at Schacht Fröschnitz 1 and Schacht Fröschnitz 2 was formally commenced on 23 July 2015. Both shafts were sunk by blasting to approximately 400 metres depth, with a diameter of approximately 10 to 11 metres.
2017
Construction

Underground cavern completed; tunnel drives launched

The underground cavern at the foot of the two shafts was completed, and untertägige (underground) tunnel drives in both directions began from the cavern in 2017.
2018
Construction

Tunnel boring machines "Carl" and "Ghega" launched towards Gloggnitz

On 13 July 2018 the two tunnel boring machines "Carl" and "Ghega" — each 120 metres long and 2,500 tonnes, with a boring diameter of about 10 metres — began driving eastward towards Gloggnitz from the Fröschnitzgraben cavern.
2022
Construction

First breakthrough between Fröschnitzgraben and Göstritz sections

In early June 2022 the first underground breakthrough was achieved between the Fröschnitzgraben and Göstritz construction sections, creating the first connection between the two tunnel lots.
2024
Construction

Final tunnel breakthrough completed

The final breakthrough of the entire Semmering-Basistunnel was achieved on 29 November 2024, completing all tunnel drives. Finishing works and technical fitout of the tunnel then commenced.
2029
Operation

Tunnel scheduled for opening; shafts to serve as permanent ventilation infrastructure

The Semmering-Basistunnel, including the underground emergency stop station in the Fröschnitzgraben cavern, is scheduled to open with the December 2029 timetable change. The access shafts not required for operational rail use are being filled with concrete during the finishing phase; those retained will serve as ventilation shafts for the emergency stop.

Sources and records

German Wikipedia: Semmering-Basistunnel
ÖBB-Infrastruktur AG: Tunnel Section Fröschnitzgraben (official project page)
ÖBB-Infrastruktur AG: Aktuelles Semmering (project updates page)
Implenia AG: Semmering Basistunnel SBT Los 2.1 (project reference)
Meinbezirk.at: Schachtarbeiten haben begonnen (July 2015)
ORF.at: Komplexes Innenleben – Neue Bauphase im Semmering-Basistunnel
Verkehrs-Server des Landes Steiermark: Semmering-Basistunnel – Bau der Tunnel-Schächte
tunnel-online.info: Start of Work on the Tunnel Shafts at Lot 2.1, Fröschnitzgraben
This researched site record is part of the HAABase Mines database. Normal personal research and browsing is welcome. Automated bulk extraction, republication, or harvesting of site text and images is not permitted without written consent.