Site overview

The Schachtanlage Asse II is a former potash and rock-salt mine on the Asse ridge, ten kilometres south-east of Wolfenbüttel in the Landkreis Wolfenbüttel, Niedersachsen. The older of its two surface shafts, Schacht Asse II, was sunk in 1906; Schacht Asse I had already been sunk in the same ridge and was abandoned in 1906, and Schacht Asse III followed but was given up in 1924. Schacht Asse II served the commercial extraction of potash and rock salt from 1909 until 1964.

In 1965 the Gesellschaft für Strahlenforschung (GSF), acting for the federal government, purchased the former mine for 750,000 DM and began using it as a research facility for the underground disposal of radioactive waste. Between 1967 and 1978, approximately 125,787 containers — representing around 47,000 cubic metres of low- and intermediate-level radioactive waste — were emplaced in thirteen former mining chambers on the 511-, 725-, and 750-metre levels. Many containers were already damaged at the point of emplacement.

Research into high-level waste disposal in salt continued until 1995. Saltwater infiltration and serious structural instability — consequences of the intensive historical salt extraction — progressively undermined the integrity of the installation. In 2008 it became publicly known that radioactively contaminated salt solutions had been pumped to the 975-metre level without radiation-protection authorisation.

The Bundesamt für Strahlenschutz became operator in 2009 under nuclear law. In 2013 the Bundestag passed the Lex Asse, legally mandating retrieval of all radioactive waste and the subsequent decommissioning of the mine. The BGE, which took over as operator in 2017, plans to retrieve the first containers no earlier than 2033.

Retrieval costs are estimated at four to six billion euros.

The shaft site lies on the Asse ridge in open rural surroundings, where the former mine reads as an enclosed technical compound set apart from the surrounding agricultural landscape.

Map

Map markers and directions links are provided for location reference only and do not indicate public access or permission to enter a site.
No site photograph is currently available. Images will be added as field visits are carried out.

History

The Schachtanlage Asse takes its name from the Asse ridge, a low hill in the Landkreis Wolfenbüttel rising to approximately 240 metres. The geological structure below the ridge is a salt stock of Zechstein origin. Two shaft installations were developed to exploit the potash and rock-salt deposits beneath it.

Schacht Asse I was already being worked and was abandoned in 1906. Schacht Asse II — to which the complex's common name refers — was sunk from 1906; after sinking was complete the shaft was used for commercial extraction of potash and rock salt from 1909. During the operational period the extraction chambers were mined with the intensity typical of the German potash industry, which left the rock mass perforated with large open voids. Commercial extraction continued until 1964. Schacht Asse III was a later addition but was abandoned in 1924. The abandonment of Asse I and III for water ingress — both had become flooded with water after closure — was later considered significant context for the long-term behaviour of the salt stock as a whole.

In 1965, the GSF (Gesellschaft für Strahlenforschung), acting on behalf of the federal government, purchased the salt mine for 750,000 DM and established the Institut für Tiefenlagerung radioaktiver Abfälle, intended to research and demonstrate the permanent underground disposal of radioactive waste in a salt formation. Because the Federal Republic was preparing to enter large-scale commercial nuclear power generation and needed a disposal route for the resulting radioactive waste, the dry and geologically stable conditions in the salt were considered an ideal environment.

Between 1967 and 1978, approximately 125,787 containers of low- and intermediate-level radioactive waste, representing about 47,000 cubic metres, were emplaced in thirteen former extraction chambers. Two chambers lie at 725 metres depth in the middle section of the mine, ten chambers lie in the southern flank at 750 metres depth, and a further chamber is at 511 metres. The waste came from nuclear power stations, research institutions, and industrial users across the Federal Republic. From 1967 to 1975, no charges were levied for the emplacement of approximately half the containers; from December 1975, tariffs of 150 to 3,700 DM per container were charged. In total, 16.5 million DM was collected. Emplacement methods were progressively degraded over the three phases of operation: containers were initially placed upright on one another, then tipped on their sides, and finally dropped from a height down salt slopes into the chambers, with known damage to containers accepted from this point. Retrieval was explicitly not planned. In 2009 it was publicly revealed that approximately 29 kilograms of plutonium had been emplaced — substantially more than the 9 kilograms previously disclosed.

Following the end of waste emplacement in 1978, research into the geological and engineering aspects of disposing of highly radioactive waste in salt continued at the Schachtanlage Asse II until 1995. Remaining open voids from the historical salt extraction were backfilled between 1995 and 2004. In 1997 the federal government decided to close the shaft under mining law (Bergrecht), using solid fill as the intended closure method.

From 2005 to 2008, radioactively contaminated brine solutions were pumped from their collection points to the 975-metre level without the legally required radiation-protection permit. When this became publicly known in mid-2008, the federal government reversed the closure strategy and resolved instead to close the mine under nuclear law (Atomrecht). On 1 January 2009 the Bundesamt für Strahlenschutz (BfS) became the new operator. An analysis of closure options in 2010 concluded that only retrieval of the radioactive waste could satisfy the legally required demonstration of long-term safety. The Lower Saxon Landtag voted for retrieval in 2012, and in April 2013 the Bundestag passed the Lex Asse — the Gesetz zur Beschleunigung der Rückholung radioaktiver Abfälle und der Stilllegung der Schachtanlage Asse II — with a broad parliamentary majority, legally mandating retrieval before final decommissioning.

On 25 April 2017 the Bundesgesellschaft für Endlagerung mbH (BGE), a wholly state-owned company, became the operator, taking over from the BfS. The BGE published its retrieval plan in April 2020. The plan requires sinking a new shaft (Schacht 5) and constructing horizontal connection roadways to allow access by more workers and larger equipment, together with a waste treatment facility and an interim storage site near the Asse. Saltwater infiltration continues: the principal inflow collection point registered approximately twelve litres per hour in 2008; by 2024 the rate at the main collection level had decreased, but water was being intercepted in greater quantities in deeper zones above the emplacement chambers. The Entsorgungskommission assessed in a 2020 report that the timescales for planning, approval, and implementation are demanding, that reliable information about the condition of the emplacement chambers and the containers is lacking, that many containers are severely damaged, and that significant radiation exposures for workers and nearby populations must be anticipated over the decades of retrieval. The first containers are not expected to be retrieved before 2033. Final decommissioning is projected for the 2050s–2060s. Remediation costs are estimated at four to six billion euros; these are to be borne by the federal government, not the waste producers. An information centre (Infostelle Asse) near the mine entrance provides public exhibitions and lectures on the retrieval programme.

Timeline

1906–1909
Construction

Schacht Asse II sunk; commercial extraction commences 1909

Schacht Asse II was sunk from 1906. Commercial extraction of potash and rock salt from the salt stock began in 1909. The neighbouring Schacht Asse I had already been abandoned in 1906, and Schacht Asse III was sunk later but abandoned in 1924.
1909–1964
Operation

Potash and rock-salt extraction; intensive chamber mining creates large underground voids

Commercial potash and rock-salt extraction continued from 1909 to 1964. The intensive chamber mining method left the salt mass with extensive open voids, which later compromised both rock stability and the watertightness of the overlying strata.
1965
Legislation

GSF purchases the mine; Institut für Tiefenlagerung established

In 1965 the Gesellschaft für Strahlenforschung (GSF), acting for the federal government, purchased the former mine for 750,000 DM. The Institut für Tiefenlagerung radioaktiver Abfälle was established to demonstrate underground disposal of radioactive waste in salt formations.
1967–1978
Operation

Approximately 125,787 containers of low- and intermediate-level radioactive waste emplaced

From 1967 to 1978, approximately 125,787 containers (c. 47,000 cubic metres) of low- and intermediate-level radioactive waste were emplaced in thirteen former mining chambers at depths of 511, 725, and 750 metres. Emplacement methods degraded progressively; many containers were damaged at the point of emplacement. Retrieval was explicitly not planned.
1979–1995
Operation

Research into high-level waste disposal in salt; then research ends

Research into the disposal of highly radioactive waste in salt formations continued from 1979 until 1995, when the federal government decided to end research activities at the Schachtanlage Asse II.
1995–2004
Closure

Remaining open voids from salt extraction backfilled

Residual open extraction voids from the historical salt-mining period were backfilled between 1995 and 2004 as part of the original (pre-retrieval) closure plan.
1997
Legislation

Federal government decides to close Asse II under mining law

In 1997 the federal government resolved to close the Schachtanlage Asse II under Bergrecht, using solid fill as the intended closure method.
2008
Operation

Contaminated salt solutions pumped to 975-metre level without permit; becomes publicly known

In mid-2008 it became publicly known that radioactively contaminated brine solutions had been pumped to the 975-metre level from 2005 to 2008 without the required radiation-protection permit. The government reversed the closure strategy and resolved to close the mine under nuclear law.
2009
Legislation

Bundesamt für Strahlenschutz becomes operator under nuclear law

The Bundesamt für Strahlenschutz (BfS) became the new operator of the Schachtanlage Asse II on 1 January 2009 following a 2009 amendment to the Atomgesetz classifying the installation as a nuclear facility.
2013
Legislation

Bundestag passes Lex Asse; retrieval of radioactive waste legally mandated

In April 2013, the Bundestag passed the Gesetz zur Beschleunigung der Rückholung radioaktiver Abfälle und der Stilllegung der Schachtanlage Asse II (Lex Asse) with a broad parliamentary majority, legally mandating retrieval of all waste before final decommissioning.
2017
Legislation

Bundesgesellschaft für Endlagerung mbH (BGE) becomes operator

The BGE, a wholly state-owned company established in 2016, took over operation of the Schachtanlage Asse II from the BfS on 25 April 2017.
2020
Construction

BGE publishes retrieval plan; new shaft and waste treatment facility planned

In April 2020, the BGE published its retrieval plan. The plan requires a new shaft (Schacht 5), new horizontal connection roadways, and a near-site waste treatment facility and interim storage installation. The first containers are not expected to be retrieved before 2033; final decommissioning is projected for the 2050s–2060s.

Sources and records

Wikipedia article (German): Schachtanlage Asse
Niedersächsisches Ministerium für Umwelt, Energie und Klimaschutz: Schachtanlage Asse II — stilllegungsrechtliche Darstellung
Bundesministerium für Umwelt, Klimaschutz, Naturschutz und nukleare Sicherheit (BMUKN): Schachtanlage Asse II overview
Bundesgesellschaft für Endlagerung mbH (BGE): Kurzinformationen zur Schachtanlage Asse II; Rückholplan 2020
Bundesamt für Strahlenschutz (BASE): Schachtanlage Asse II — status and monitoring overview
Bundesanstalt für Geowissenschaften und Rohstoffe (BGR): Schachtanlage Asse II — geowissenschaftliche Begleituntersuchungen
Stiftung Leben und Umwelt / Heinrich-Böll-Stiftung Niedersachsen: Chronik: Asse II (November 2024)
Greenpeace Deutschland: Asse II — der Endlager-GAU (May 2024)
This researched site record is part of the HAABase Mines database. Normal personal research and browsing is welcome. Automated bulk extraction, republication, or harvesting of site text and images is not permitted without written consent.