Fact-checked Research reviewed and published About research status
View fact-check assessment and classification

The history, timeline and surviving-site classification shown here reflect the reviewed account.

Assessment

The record identifies the Wschodni II shaft of the former KWK Mysłowice in Mysłowice, not the separate Kleofas/Schwarzenfeld II shaft in Katowice. The mine’s nineteenth-century origins and ownership are supported by the Polish State Archives’ fonds description, while specialist mining-history material places completion of the eastern Wschodni II sinking in 1945. Contemporary mining-industry reporting establishes the different functions of Wschodni I and II and the post-extraction ventilation changes.

SRK technical procurements from 2016 through 2026 directly substantiate Wschodni II’s role in the active mine-water control installation; 2025 institutional photographs document the surviving shaft group. The core identity, survival and ongoing technical use are strongly supported. The exact shaft-construction specifications, detailed machinery chronology and precise coordinates merit further examination, while several older corporate milestones are better treated as wider colliery context than shaft-specific events.

Surviving-site classification

The site comprises the retained tall Wschodni II winding headframe, its shaft installation and associated industrial buildings within the active CZOK Mysłowice-Wesoła I pumping station. It is classified as shafts_buildings and as a former mine site with an active water-management shaft because contemporary SRK equipment-maintenance notices, dewatering project records and 2025 institutional photography document the structures and ongoing winding-related functions. Its character is mixed: historic shaft and headframe fabric survives within an altered, modernised operating complex, rather than a complete historic colliery.

The original construction date and degree of replacement of individual machinery components require detailed technical inspection.

Published 23 November 2026 · Overall confidence 89/100 · Classification confidence High
Sources added or confirmed during the review are included in Sources and records where available.

Site overview

Szyb Wschodni II is the taller of the two eastern shafts at the former Kopalnia Węgla Kamiennego Mysłowice in Mysłowice, Upper Silesia. The origins of the colliery lie in the nineteenth-century Danzig coalfield, while the consolidated Mysłowice undertaking developed in 1866. Sinking of Wschodni I began in 1923 and Wschodni II was completed in 1945.

Both later formed part of the mine’s intake ventilation system, although the adjacent Wschodni I also carried hydraulic sand-stowing pipes. Following the merger with Wesoła in 2007 and the end of coal extraction in the Mysłowice section in 2008, the eastern shaft yard continued to support underground water management and ventilation. Wschodni II remains a working winding shaft associated with the Centralny Zakład Odwadniania Kopalń (CZOK) stationary pump installation.

Its tall headframe and surviving equipment are recorded by contemporary mining-industry reports, SRK engineering procurements and an institutional photographic survey in 2025.

The surviving tower stands within a reworked industrial landscape at Mysłowice, where the shaft zone remains functional but the former mine reads as a fragmented site.

Map

Map markers and directions links are provided for location reference only and do not indicate public access or permission to enter a site.
No site photograph is currently available. Images will be added as field visits are carried out.

History

The former Kopalnia Węgla Kamiennego Mysłowice grew from the nineteenth-century development of coalfields around Mysłowice in Upper Silesia. Mining rights in the Danzig field are traced to 1837, but the consolidated mine known as Mysłowice was formed in 1866 through the combination of the Danzig mine and the Neu Danzig field. Other mining fields were subsequently incorporated, and extraction expanded beneath parts of Mysłowice and the surrounding industrial district. This distinction between the early concessions and the later consolidated colliery is important to the history of the eastern shafts, which were built much later as part of a complex that had developed over many decades.

The undertaking was initially associated with Gewerkschaft Myslowitz. According to the State Archives' description of the Mysłowice records, it entered the Katowice mining and metallurgical company in 1881 and, from 1937, formed part of Wspólnota Interesów Górniczo-Hutniczych. In 1940 it came under the Upper Silesian mining administration of the Reichswerke Hermann Göring organisation, before passing to Katowickie Zjednoczenie Przemysłu Węglowego after 1945. These changes affected the whole mine rather than representing separate construction phases at Wschodni II.

The earlier shaft network developed in stages. Shafts begun in the 1870s included Gustaw, Kate and Luisa, later known respectively as Jagiełło, Łokietek and Sas; the Otto ventilation shaft, later Bończyk, followed in 1911. As the underground working area expanded, new infrastructure became necessary farther east of the older pithead. Work on Wschodni I began in 1923 and mining-history accounts drawing on surveying records place the completion of Wschodni II sinking in 1945. The two shafts became a distinct eastern operating group within the wider mine, with Wschodni II distinguished by its considerably taller winding headframe.

The adjacent shafts had overlapping but not identical duties. Wschodni I was used to convey hydraulic stowing material underground: sand mixed with water was delivered through pipes to fill selected worked-out voids and reduce subsidence risks. The pipework and compact winding installation of Wschodni I remained characteristic features of the shaft. Both Wschodni I and Wschodni II also functioned as intake shafts, bringing fresh air into the underground ventilation circuit. Wschodni II had its own winding installation and a more prominent headframe; its continuing winding equipment is evidenced by the technical maintenance programme of the later pumping station. The distinction matters because many published technical details about the very small Wschodni I headframe, its winding machine and its stowing pipework do not describe Wschodni II.

During the later twentieth century the mine continued under changing corporate structures, joining Katowicki Holding Węglowy in the post-socialist reorganisation period. On 1 January 2007 it merged with KWK Wesoła to form Mysłowice-Wesoła, with the older workings administered as Ruch Mysłowice. Extraction from that section ended on 7 November 2008, bringing to a close more than a century of industrial coal production associated with the Mysłowice colliery. That cessation did not remove the need to ventilate connected workings or control the accumulation of mine water. The eastern shafts consequently remained relevant to the operation and protection of the underground system even after coal was no longer raised from the former Mysłowice production section.

In 2015 the Mysłowice section entered the restructuring and liquidation programme administered by Spółka Restrukturyzacji Kopalń (SRK). Demolition and transfer affected substantial parts of the old main pithead elsewhere in Mysłowice, including buildings around shafts such as Łokietek, but the eastern shaft yard followed a different course. Its retained equipment was required for the ongoing safety and dewatering arrangements. A 2016 SRK procurement specifically concerned the design of mine-water discharge infrastructure linking Wschodni II to the River Przemsza, directly identifying the shaft in the water-management system. Further SRK technical procurements refer to compressed-air equipment and to the winding machinery of Wschodni II.

A major modernisation programme was reported in 2022. It involved the two eastern shafts and their common services, with new electrical infrastructure, personnel facilities and a new main fan station at Wschodni I. Before the change, both shafts supplied intake air, while the Południowy shaft provided exhaust ventilation. The plan was to convert Wschodni I to an exhaust role as Południowy was retired. Contemporary reports described a proposed service horizon for Wschodni I extending at least to 2041; this was a stated planning assumption for the neighbouring shaft, not a dated closure schedule for Wschodni II. The works were organised around an operating pumping installation, and contemporary mining-industry reporting emphasised the need to maintain continuous operation of both eastern winding systems and their supporting equipment.

Wschodni II remains within the CZOK Mysłowice-Wesoła I stationary pumping facility, serving the mine-water control system rather than commercial coal extraction. SRK's maintenance procurement covers winding machinery at both eastern shafts, and notices issued in 2026 specifically concern the Wschodni II hoist recording equipment for work in 2027. This documentary record demonstrates that the retained winding installation has a continuing operational purpose. A photographic survey made in 2025 by Adam Rostecki for the Regionalny Instytut Kultury im. Wojciecha Korfantego records the headframes, machinery buildings and shaft yard as part of the working CZOK premises.

The higher headframe of Wschodni II continues to dominate this part of the industrial landscape, standing beside the unusually low headframe of Wschodni I. Their survival makes the eastern shaft complex a particularly clear example of how elements of a closed coal mine can retain essential technical functions long after extraction has ceased. The two structures also preserve the evidence of their different duties within the colliery: the smaller shaft with its former stowing arrangements and later ventilation equipment, and the taller Wschodni II with its winding installation supporting the ongoing water-management operation.

Timeline

1923
Construction

Construction begins at neighbouring Wschodni I

Sinking began at Wschodni I, establishing the eastern shaft group that later included Wschodni II.
1945
Construction

Wschodni II sinking completed

Historical mine-shaft accounts date completion of the sinking of Wschodni II to 1945.
2007
Operation

Mysłowice and Wesoła merge

On 1 January 2007 the mine merged with Wesoła. Wschodni II remained within the eastern operational shaft group of the Mysłowice section.
2008
Closure

Coal extraction ends at Ruch Mysłowice

The Mysłowice extraction section produced its last coal on 7 November 2008; Wschodni II continued to serve essential shaft and safety functions.
2015
Closure

Eastern shaft site enters SRK management

In 2015 former Mysłowice installations, including Wschodni II, entered the SRK restructuring and mine-water management framework.
2016
Redevelopment

Mine-water discharge scheme for Wschodni II

SRK commissioned technical design for conveying mine water from Wschodni II to the Przemsza, documenting its continuing water-management role.
2021
Construction

Eastern shaft zone modernisation begins

Design and construction work for the Wschodni I and II shared installation began in 2021–22, incorporating new power services, pumping-station accommodation and an exhaust fan station at Wschodni I while the Wschodni II winding system remained in operation.
2025
Heritage

Eastern shafts recorded in institutional survey

An institutional photographic record documents Wschodni I, Wschodni II and their winding and pumping-site buildings within the CZOK facility.

Sources and records

This list includes live sources already held for the record and any additional sources added or confirmed during the published fact-check review.

Further sources

Research bibliography

Polish Wikipedia article: Kopalnia Węgla Kamiennego Mysłowice
Polish Wikipedia article: Kopalnia Węgla Kamiennego Mysłowice-Wesoła
Historical blog article: Fedrowała węgiel ponad 170 lat. KWK Mysłowice (mojhistorycznyblog.pl)
netTG.pl article: Zabudowania szybu Wschodniego I miały zostać zlikwidowane (2022)
netTG.pl article: Likwidacja, ale też inwestycja — modernisation of eastern shaft zone
netTG.pl article: Oddział SRK Mysłowice-Wesoła I zbliża się do końca procesu likwidacji
Śląska Opinia: Likwidacja części kopalni Mysłowice ruszyła (April 2021)
netTG.pl article: Co dalej z likwidowaną kopalnią Mysłowice (2018)
The Beauty of Steel: KWK Mysłowice profile
This researched site record is part of the HAABase Mines database. Normal personal research and browsing is welcome. Automated bulk extraction, republication, or harvesting of site text and images is not permitted without written consent.